Introdcution

The Power Outages dataset contains records of major electricity outages across the continental U.S. In addition to the outage details, it includes information about the location, local climate, land use, electricity consumption, and economic characteristics of the affected regions. This added context helps paint a fuller picture of the conditions surrounding each outage. With this data, it’s possible to explore what factors might influence how long outages last.

Source: Link to Dataset

This dataset will allow us to answer the question above.

Data Cleaning

Missing Value Handling

The first step was to check if the dataset contained any missing values. This led to the identification of 25 columns that contained missing values. Out of these columns, the ones that needed to be handled since they would be used later in the analysis were:

This led to considering whether there were possibilities for imputing or dropping the missing values based on context. But since the amount of missing values was small and the dataset had a large number of observations, ultimately dropping was the decision that was made. Additionally, with Outage Duration, there was an attempt to compute the values using the OUTAGE.START.TIME column and the OUTAGE.RESTORATION.TIME column, but more analysis showed that the missing values for Duration were the same for those two columns as well.

Data Type Converting

Data Type Fixes

After the missing values were handled, there were a couple of columns of interest that also had data types that needed to be changed.

Here is look at the dataset with the relavant columns

YEAR Month STATE NERC.REGION CLIMATE.CATEGORY CAUSE.CATEGORY POPULATION Outage Duration OUTAGE.START.HOUR
2011 July MN MRO normal severe weather 5348119 51 17
2014 May MN MRO normal intentional attack 5457125 0.0166667 18
2010 October MN MRO cold severe weather 5310903 50 20
2012 June MN MRO normal severe weather 5380443 42.5 4
2015 July MN MRO warm severe weather 5489594 29 2

Exploratory Data Analysis

With a cleaner data set, now we can explore it.

Month Outage Duration
January 63.1088
February 43.9497
March 58.8111
April 25.6159
May 36.4599
June 34.3185
July 38.7338
August 42.7389
September 76.569
October 62.3239
November 30.1119
December 55.9322

The table shows the mean outage duration in each month. There are some clear patterns between the month and how long an outage lasts, with the maximum in September, which lines up with hurricane season. It also follows that the mean durations during that season are similar as well. This might be useful when discussing if months or season will be better for predicting the outage duration.

The histogram shows a very right-skewed distribution, which is expected. Additionally, there are several large outliers that create a very long tail on the histogram. For example, the maximum outage duration was 1810 hours. This is much larger than the highest bin which had values from 0-24 hours.

Overall, the result is expected as severe weather caused the most outages. But “intentional attack” being the second most common is very surprising. Intentional attack refers to a situation where officials determine that targeted human actions caused the outage. Additionally, the disribution of the bottom 5 categories are simliar so it will help during future model prediction.

You can see that the Midwest gets hit the worst when it comes to outage length. Places like Wisconsin and West Virginia have way longer average durations than most other states. That kind of pattern makes me think state info could actually help when predicting outage time. If some states always take longer to fix things, it’s probably worth including that in the model.

Even though severe weather was the largest category causing outages, it isn’t first in duration. Fuel supply emergencies have a significantly longer average outage duration. This again could help in the model. Also, the categories that had mean outage durations lasting more than a day were public appeal, equipment failure, severe weather, and fuel supply. The rest were usually resolved sooner.

Framing a Predicion Model

## The Question: Based on the factors that are known at the start of a outage, how long will the power outage last?

What type of problem is this?

This is going a regression problem, as we predciting a continous variable.

How will this be tested?

First we will create a training set, and and independent testing set. This will allow use to truly measure the accuary of our model. Using both mean squared error and mean absolute error.

A Basic Model

Using the dataframe from earlier, a simple model was created.

Features Used in the Baseline Model

The following features were used:

(OHE) represents features that we One Hot Encoded

The Results:

Metric Value
RMSE 164.355
MAE 74.5021
Mean Outage Duration 46.198
TMSE 108.876

The model performed very badly, it was wrose than predicting the mean each time as the TMSE was better than the RMSE. This needs to be improved.

Final Model

Rethinking the Model:

The first thing that comes to mind is multicollinearity, as several features in the model are highly correlated—such as CAUSE.CATEGORY, CLIMATE.CATEGORY, and NERC.REGION. This can cause unstable predictions that are overly generalized to the test set.

This means we either need to switch our features or use a different model. Ultimately, a different regression model was chosen. Instead of Linear Regression, a Lasso Regression was used. This decision was based on two reasons:

  1. Its ability to “turn off” irrelevant features by assigning them zero weights.
  2. Its ability to protect against multicollinearity by adding regularization to the coefficient matrix.

Feature Engineering

In addition to the model being changed, two new features were created:

K Folds CV:

Since the model was changed to Lasso, we needed to pick the optimal lambda so the model could perform its best. This led to using the GridSearchCV function, which allowed for k-fold cross-validation to find the best regularization strength.

The Results:

Best alpha: 0.1

Metric Value
RMSE 99.485
MAE 43.7279
Mean Outage Duration 46.198
TMSE 108.876

The final Lasso regression model performed noticeably better than simply predicting the mean outage duration. The model achieved a Root Mean Squared Error (RMSE) of approximately 164.36 and a Mean Absolute Error (MAE) of about 74.50. This compares favorably to the Total Mean Squared Error (TMSE) baseline of 108.88, which represents the error if we had predicted the average outage duration for every instance. This shows that the model is capturing some underlying structure in the data beyond the mean.